Project Timeline

2019

October 15, 2018 - March 30, 2019

  • Brightspace and Canvas sandbox access for faculty, staff and students.

Spring  

Summer

  • IT Project Team produces summary reports from all evaluation tools, and provides to LMS Advisory Committee
  • LMS Advisory Committee recommends LMS candidate to VPIT
  • VPIT recommends LMS candidate to TSUS Board of Regents
  • TSUS Board of Regents approval
  • VPIT announces approved LMS

Fall

  • IT Project Team implements new LMS
  • ITAC staff preparation support and system training
  • On-line course migration preparation
  • Public training available for faculty

2020

Spring

  • New faculty begin teaching in new LMS
  • Voluntary faculty migration of courses
  • ITAC migration support and training

Summer – Fall  

  • Requisite faculty migration of courses
  • ITAC faculty open training lab   

Fall

  • Sakai - no new site creation (read-only state)

2021

Spring – Fall

  • All courses taught in new LMS
  • Sakai archival access to course materials
  • Project site transition to new environment

2023  

January 1, 2023

    Sakai decommissioned

 


Past milestones

2018

August - December

  • Development and Integration evaluation
  • Faculty “Sandbox” evaluation
  • Accessibility evaluation
  • Security evaluation
  • Prepare pilot production environment
  • Clumping and clustering of project site use cases

June – July

  •     Pilot contract review
  •     VPIT approves pilot contracts
  •     Finalists establish evaluation environments 

April - May

  •     LMS Advisory Committee recommends pilot finalists
  •     VPIT announces pilot finalists

March

January - February

2017

December

  • Evaluate vendor responses (completed)

October

  • RFP posted for vendors (completed)

May

April

  • Overview presentations to Council of Deans and Faculty Senate (completed)